Design, Procurement and Supervision Consultant: Enviros Consulting
Construction Quality Assurance: Rowe Environmental
Date: June 2006 - September 2006
Duration of Construction Works: 14 weeks
Video: Click on the image below to view the Landfill Restoration slideshow for 2006:
Description: The work comprised:
general re-contouring the landfill waste
construction of a low permeability mineral liner from clay won from a local borrow pit, transportation to site, with compaction and
quality control to EPA requirements
installation of perimeter bunds incorporating landfill gas extraction pipework, surface water/subsoil drainage pipework, and leachate
drainage
installation of sub-soil drainage using a geocomposite filter and drainage void forming material (Pozidrain®)
importataion and grading to the required depth restoration sub-soil materials
geotextile and geocomposite (Enkamat® and Geogrid®) soil strengthening at all steep inclines
importation spreading and levelling of topsoil
grass seeding (Hydroseeding®).
Rowe Environmental were on site throughout, providing a full CQA service.